Latest Construction Planning and Management Multiple choice Questions and Answers pdf

31.    What estimate would you give  for the variance in above problem ?
a)    81
b)    54
c)    36
d)    9
Ans: a

32.    The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
a)    total float
b)    free float
c)    interfering float
d)    independent float
Ans: d

33.    The time with which direct cost does not reduce with the increase in time is known as
a)    crash time
b)    normal time
c)    optimistic time
d)    standard time
Ans: b

34. The time corresponding to minimum total project cost is
a)    crash time
b)    normal time
c)    optimistic time
d)    between normal time and crash time
Ans: d

35.    The direct cost of a project with respect to normal time is
a)    minimum
b)    maximum
c)    zero
d)    infinite
Ans: a

36.    The reduction in project time normally results in
a)    decreasing the direct cost and increasing indirect cost
b)    increasing the direct cost and decreasing the indirect cost
c)    increasing the direct cost and indirect cost both
d)    decreasing the direct cost and indirect cost both
Ans: b

37.    Economic saving of time results by crashing
a)    cheapest critical activity
b)    cheapest non-critical activity
c)    costliest critical activity
d)    costliest non-critical activity
Ans: a

38.    The process of incorporating changes and rescheduling or replanning is called
a)    resource levelling
b)    resource smoothening
c)    updating
d)    critical path scheduling
Ans: c

39.    Slack time refers to
a)    an activity
b)    an event
c)    both event and activity
d)    none of the above
Ans: b

40.   The normal time required for the comple-tion of project in the above problem is
a)    9 days
b)    13 days
c)    14 days
d)    19 days
Ans: c

Read More Questions:
Construction Planning and Management MCQs Part1
Construction Planning and Management MCQs Part2